The Irish National Road Authority’s $1.2 million, 14-mile plan

Technology makes road upgrade to two-lane highway, six-mile local road realignment, seven miles of accommodation access tracks, 14 new bridges, a grade-separated junction, and an at-grade roundabout junction more efficient and cost-effective.

 

by Jeff Winke, written on behalf of Trimble

The National Road Authority in Ireland has a plan. It intends to upgrade the N18 Limerick to Galway road to a new two-lane highway with hard shoulder. Lollygagging sheep beware.

Currently, work being done on a $1.2 million, 14-mile section extending from Ballinger’s Corner, north of Gort to Cragard, south of Crusheen, where it will tie into the existing N18 Ennis bypass. The project also includes a six-mile local road realignment, seven miles of accommodation access tracks, 14 new bridges, a grade-separated junction, and an at-grade roundabout junction.

The route selection, Environmental Impact Assessment, and roadway design were all completed by Babtie Pettit, Ltd., Limerick, Ireland. The proposed road plan was designed with the following objectives:

  • Alleviating traffic problems with respect to capacity and safety on the existing route.
  • Accommodating traffic needs for the future.
  • Improving access between Ennis, Limerick, Shannon, and Galway.
  • Improving journey times for those using the N18 route.
  • Improving traffic distribution on the road network of the area.
  • Improving environmental conditions along the existing route.

About 425 acres of land will be required for construction of the road, which is expected to take three years. The joint venture between Siac Construction based in Dublin, Ireland, and the civil engineering contractor Wills Bros Ltd. from County Mayo, Ireland, was responsible for building the roadway.

Leicestershire, England-based Bardon Composite Pavements, part of the Aggregate Industries group of companies, won the contract to mix and place 94,000 cubic yards of cement bound granular materials (CBGM) base and complete the finished road surface with a blacktop that is bonded to the CBGM.

“To supply the CBGM required, we put a production facility on site to mix the raw aggregates for the 7-inch sub-base layer,” says Richard Needham, operations director for Bardon Composite Pavements.  “This sub-base is critical because it is the main load-bearing layer of the road construction.”

The Ireland Road Authority's 14-mile, $1.2 million project for road upgrades

The National Road Authority in Ireland plans upgrade the N18 Limerick to Galway road to a new two-lane highway with hard shoulder. Work is currently being done on 14-mile section extending from Ballinger’s Corner, north of Gort to Cragard, south of Crusheen, where it will tie into the existing N18 Ennis bypass. The $1.2 million project also includes a six-mile local road realignment, seven miles of accommodation access tracks

The Siac / Wills joint-venture employed a fleet of tipper wagons to deliver nearly 500 tons per hour to the project site. Bardon Composite Pavements was responsible for placing 95,000 cubic yards of CBGM on the 36-foot wide road and hard shoulder at a depth of 180 millimeters.

The company’s six-man paving crew used a Volvo Construction Ingersoll Rand ABG Titan 9820 paver, with its 43-foot wide capacity, equipped with a Trimble PCS900 Paving Control System, to place the material.

Bardon Composite Pavements acquired its Trimble systems through KOREC, the Trimble dealer for the U.K. and Ireland. “The Trimble PCS900 Paving Control System is a 3D automatic screed control system that allowed us to directly reference off the road design,” says Carl McCoiv, contract manager with Bardon Composite Pavements. “It helped us achieve a very smooth final paved surface with accurate material usage.”                       

Bardon uses a Trimble SPS930 Universal Total Station to guide the paver. “The Trimble SPS930 is accurate to one arc second in the vertical and horizontal angles, which made it ideal for this two-lane highway project where the accuracy tolerance was very tight,” Needham states. “By paving the base to design correctly the first time, we definitely saved on the cost of rework and additional material Conservatively, we can save up to 12-cents-per-inch per square yard and the job size is better than 437,000 square yards.”

Needham points out that the Trimble systems allowed them to pave in a stakeless environment and save about 50 worker-hours per week. He reports that there is less surveyor time since there’s no need for placing pins and tape – everything can be captured with the Trimble SPS930 running SCS900 Site Controller Software which captures and records the surface levels.

“We’re doing the as-built survey as we go,” Needham says.

Trimble surveying equipment

The surveying systems used on the project has allowed workers to pave in a stakeless environment and save about 50 worker-hours per week.

View Full Article
comments powered by Disqus
advertisement
advertisement
advertisement