Better Bridges
Better Bridges
August 01, 2010 |
All Together Now
By Tina Grady Barbaccia
A bridge project that started out under intense scrutiny in an environmentally- sensitive area is now being cheered and even has the locals putting their own touch on the bridge.
The Oregon Department of Transportation (ODOT) credits this to using the construction manager/general contractor (CM/GC) approach — where the contractor works with an agency from the beginning of the project instead of after a design has already been developed.

The Interstate 5 deck arch type bridge over the Willamette River is a $201-million replacement project located at milepost 192.7, where it crosses the river between the cities of Eugene and Springfield. It was funded by the 2003 Oregon Transportation Investment Act and the federal Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) program.
“The biggest advantage [to using a CM/GC approach] is the flexibility to balance the public’s expectations while maintaining the level of public participation the owner wants to provide,” explains Kevin Parrish, project manager with Springfield, Ore.,-based Hamilton Construction, which is the construction manager/general contractor on the bridge project.
Traditionally, an agency would determine a project’s scope, the project design, and the schedule. Then, the amount of money to be spent on a project was determined. “A designer would work up the project, put it out to bid, and the contractor with the lowest price would get the project,” Parrish explains. “Then the public would see it.” With the CM/GC approach, the contractor is involved in the entire process. This approach isn’t new. It’s common in the private sector, but for DOTs, it’s considered to be an innovative approach.

“We hire the contractor at the start of the design,” explains Dick Upton, major projects unit manager for ODOT and project manager for the I-5 bridge project. “As construction manager, he [the contractor] and his team work with us through design, fundamentally giving constructability reviews and more or less guiding our construction approach to the way he would prefer to approach the job.”
This is a pilot program for ODOT, and one of the first times this approach has ever been used on horizontal construction. “Before we launched down this path, we did a scan of agencies doing it,” he says. Only Arizona and Utah were currently using the CM/GC approach. “Now Nevada is calling and asking questions [about our approach] too,” Upton says.
Vocal locals
Involving the public from the start was a must.
“In Eugene, members of the community take a high interest in publicly-funded projects,” Parrish says. “The locals are very vocal.”
ODOT is using the high level of interest in the project to help shape the design of the bridge and the surrounding natural area. “There have been some projects that haven’t gone over as well, and ODOT has learned from that,” Parrish says. “ODOT wants to serve the public good. A project that could have generated a lot of negative publicity is now providing eagerly anticipated improvements and enhancements to the surrounding area.”







